Please use caution when traveling in the area of Blue Ridge Avenue. A detour will be in place daily.
Construction Project Update: Blue Ridge Ave - Phase 3 Work
Sewer replacement work on Blue Ridge Avenue will begin on or after Tuesday March 23. DOLI Construction Corp will be performing the work.
To perform this work safely, DOLI will close Blue Ridge Avenue and establish a detour (See Image). Residents located within the road closure on Blue Ridge Avenue will be able to access their property. DOLI is required to maintain access to all properties during this work, but there may be some coordination required between the property owner and DOLI.
Please stay alert and pay close attention to the signs while navigating through this area over the next month. The road will reopen at the end of each day. We appreciate your patience during our important construction project.
Questions? Call 717-657-5617 or email mynewsewer@lowerpaxton-pa.gov.