Bridge Update from PennDOT - Exit 50 Interchange - July 24, 2018

Good News with Changes Coming This Week for I-83 Exit 50 Interchange Project Near Colonial Park

-- Westbound motorists on Route 22 will soon be able to turn south on I-83; and motorists from southbound I-83 will soon be able to turn left onto Route 22. --

Harrisburg, PA – There is good news to report this week for the Interstate 83 Exit 50 project near Colonial Park in Dauphin County, despite all the rain we’ve received lately. This morning, the new traffic signal on Route 22, located at the end of the off-ramp from southbound I-83, was placed on flash. The intent is to alert motorists to the presence of this new traffic signal. This traffic signal will become operational in a few days with its green, yellow and red phases. Weather permitting, the following two significant changes should be accomplished later this week:

• By week’s end, we should be in position to restore the connection between the off-ramp from southbound I-83 to Route 22 at the traffic signal so that motorists can turn left onto eastbound Route 22.  This movement hasn’t been available to motorists since June 17, and motorists have had to be detoured to I-83 Exit 48 (Union Deposit Road) and back on northbound I-83 to access eastbound Route 22 since then.

• Also by week’s end, the loop ramp from westbound Route 22 to southbound I-83 will reopen. This should improve convenience and safety by eliminating the variety of “innovative” ways motorists have tried to cope with the situation by turning around at various locations along Route 22 (such as South Franklin Street, the parking lot of Dunkin’ Donuts, the parking lot of Empire Beauty School, Peach Alley, South 39th Street, etc.) to access a ramp to southbound I-83.

This work at the I-83 Exit 50 interchange is part of an overall construction contract that began in 2016 to replace three bridges that cross over I-83 in Lower Paxton Township – Elmerton Avenue (State Route 3026), Route 22 (Jonestown Road) and Union Deposit Road (SR 3020). The Elmerton Avenue bridge was rebuilt in 2016. Construction of the Union Deposit Road bridge at I-83 Exit 48 wrapped up last fall. The Route 22 bridge at the I-83 Exit 50 interchange should be substantially complete by the end of this year. All three new bridges will provide greater lateral under clearance to provide the width necessary to widen I-83 to six lanes. The I-83 widening project is currently scheduled to start late this year and finish in 2021.

PennDOT has contracted with New Enterprise Stone & Lime Company, Inc. of New Enterprise, Pennsylvania, to conduct the three bridge replacements at a cost of $34,199,999. The overall project with the three bridges is scheduled to wrap up in spring 2019.
 

Frequently Called Numbers

Main Switchboard
717-657-5600
Police Administration
717-657-5656
Public Works Department - Jeff Kline
717-657-5615
Sewer Department - William Weaver
717-657-5617
Parks and Recreation - Terry Bauknight
717-657-5635
Supervisor's Voice-Mail
717-373-1599
Communications Department - Leigh Ann M. Urban
717-657-5600

Office Hours

Municipal Center (Administration, Community Development, & Sewer)
8:00 a.m. to 5:00 p.m.

Police Department Records Office
8:00 a.m. to 4:00 p.m.

Public Works Department
6:30 a.m. to 2:30 p.m.

Sanitary Sewer Operations
6:30 a.m. to 2:30 p.m.

Friendship Center and the Parks and Recreation Department
Monday to Thursday -  5:30 a.m. to 10 p.m.
Friday - 5:30 a.m. to 9:00 p.m.
Saturday - 7:00 a.m. to 7:00 p.m.
Sunday - 12:00 p.m. to 6:00 p.m.

Social Media